The Little Ice Age and Delay Claims

January 24, 2018
Wally Zimolong - Supplemental Conditions

Much of the Eastern United States is just now emerging from a historic two week cold snap. In much of the Northeast and Mid-Atlantic, the temperature stayed below freezing for 15 days straight. Cities recorded the lowest temperatures in a quarter century. Winter Storm Grayson reeked havoc along the Eastern Coast bringing snow to places like Charleston and a crippling blizzard to Boston.

The record cold snap also impacted the construction industry. Delivery delays, the inability to apply weather sensitive applications (like cast in place concrete), and the unavailability of labor are just a few things that extreme weather can cause on a construction project. If they happen at the wrong time, delays can destroy project schedules and make previous delays even worse. Delays cost money and can mean the difference between a profitable project from both the owner and contractors perspective.

Mr. Zimolong may be contacted at wally@zimolonglaw.com



714.701.9180

Arrange No Cost Consultation










Subscribe to Construction Defect Journal

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2018 - Construction Defect Journal – All Rights Reserved