Type I Differing Site Conditions Claim is Not Easy to Prove

Cartoon of two men working on roof

David Adelstein discusses the difficulties of claiming type I differing site conditions.

May 30, 2018
David Adelstein - Florida Construction Legal Updates

A differing site condition claim will almost universally result in both a cost and time impact. There will be additional, unanticipated costs incurred. And there will likely be a delay requiring additional time to perform.

A Type I differing site condition claim is when the contractor encounters conditions at the site different than those indicated in the contract documents. That seems easy enough to prove, right. Nope. And, I mean nope! If you don’t believe me, consider the recent decision in Meridian Engineering Co. v. U.S., 885 F.3d 1351 (Fed.Cir. 2018).

Mr. Adelstein may be contacted at dadelstein@gmail.com



714.701.9180

Arrange No Cost Consultation










Subscribe to Construction Defect Journal

Construction Defect Journal Archives - Recent CD News for Construction Claims Professionals

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2024 - Construction Defect Journal – All Rights Reserved