Under the Contract Disputes Act (41 USC 7101 en seq.), when a contractor submits a claim to the government in excess of $100,000, the claim MUST contain a certification of good faith, as follows:
For claims of more than $100,000 made by a contractor, the contractor shall certify that–
(A) the claim is made in good faith;
(B) the supporting data are accurate and complete to the best of the contractor’s knowledge and belief;
(C) the amount requested accurately reflects the contract adjustment for which the contractor believes the Federal Government is liable; and
(D) the certifier is authorized to certify the claim on behalf of the contractor.
41 U.S.C. 7103(b)(1). See also 48 C.F.R. s. 33.207(c) as to the wording of the certification.
The contracting officer is not required to render a final decision on the claim within 60 days if, during this time period, he/she notifies the contractor of the reasons why the certification is defective. 41 U.S.C. 7103(b)(3). Importantly, the contracting officer’s failure to render a decision within 60 days is deemed an appealable denial.
Mr. Adelstein may be contacted at dma@kirwinnorris.com