Certifying Claim Under Contract Disputes Act

Businessman signing contract

When a contractor submits a claim to the government in excess of $100,000, the claim must contain a certification of good faith.

June 8, 2020
David Adelstein - Florida Construction Legal Updates

Under the Contract Disputes Act (41 USC 7101 en seq.), when a contractor submits a claim to the government in excess of $100,000, the claim MUST contain a certification of good faith, as follows:

For claims of more than $100,000 made by a contractor, the contractor shall certify that–

(A) the claim is made in good faith;

(B) the supporting data are accurate and complete to the best of the contractor’s knowledge and belief;

(C) the amount requested accurately reflects the contract adjustment for which the contractor believes the Federal Government is liable; and

(D) the certifier is authorized to certify the claim on behalf of the contractor.

41 U.S.C. 7103(b)(1). See also 48 C.F.R. s. 33.207(c) as to the wording of the certification.

The contracting officer is not required to render a final decision on the claim within 60 days if, during this time period, he/she notifies the contractor of the reasons why the certification is defective. 41 U.S.C. 7103(b)(3). Importantly, the contracting officer’s failure to render a decision within 60 days is deemed an appealable denial.

Mr. Adelstein may be contacted at dma@kirwinnorris.com



714.701.9180

Arrange No Cost Consultation










Subscribe to Construction Defect Journal

Construction Defect Journal Archives - Recent CD News for Construction Claims Professionals

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2024 - Construction Defect Journal – All Rights Reserved