Both owners and contractors engaged in private works construction should ensure their teams are aware of this new law and be prepared to comply with its procedures.
March 24, 2026
—
Michael J. Baker - Snell & Wilmer
For private works construction contracts entered on or after January 1, 2026, recent legislation establishes a claims and dispute resolution process for change orders. The law is codified at Civil Code § 8850. A synopsis of the pertinent provisions includes the following:
- Submitting a Claim. Contractors or subcontractors must submit a detailed, documented claim when requesting additional time or payment.
- Owner’s Response Time. The owner must meet and confer within thirty (30) days after receiving the claim. Within ten (10) days of meeting, the owner must provide a written statement identifying which portions of the claim are undisputed and which are disputed. An owner’s failure to respond is treated as disputing the entire claim.