The DoD recently issued a memorandum to COs guiding the use of economic price adjustment clauses to address inflation-related cost increases.
The Department of Defense (“DoD”) recently issued a memorandum to contracting officers (“COs”) guiding the use of economic price adjustment (“EPA”) clauses to address inflation-related cost increases. The memorandum, entitled Guidance on Inflation and Economic Price Adjustments, comes as the year-over-year inflation rate rose to 8.6% in May, and contractors with fixed-price contracts seek ways to recover their rising costs. EPA clauses allow the parties to mitigate cost risks that present themselves as a result of circumstances beyond the contractor’s control, e.g., inflation and supply chain price fluctuations. Generally, an EPA clause will dictate that the Government bear the cost risk up to a mutually agreed-upon ceiling. EPA clauses apply to the cost portion of a contract, but do not normally apply to the profit. DFARS PGI 216.203-4.
Memorandum: No CO Authority to Grant Contractual Relief Absent an EPA Clause
The memorandum states that absent an existing EPA clause, COs do not have the authority to provide contractual relief for unanticipated inflation under a firm-fixed-price contract.
Reprinted courtesy of Jennifer Harris, Peckar & Abramson, P.C. (ConsensusDocs) and Abby Salinas, Peckar & Abramson, P.C. (ConsensusDocs)
Ms. Harris may be contacted at jharris@pecklaw.com