They’re called deadlines for a reason. Usually, because something really bad could happen if you fail to meet the deadline.
For those in the construction industry, you probably aware of the “deadline” to bring a claim for latent defects (10 years from substantial completion); the deadline to file suit to foreclose on a mechanics lien (90 days from the date of recording the mechanics lien), and the deadline for serving a preliminary notice (generally, 20 days from the date labor and/or materials are first furnished).
Well, here’s another deadline: Under Code of Civil Procedure section 585.310, you have 5 years after a complaint is filed to bring a case to trial, absent the court granting relief. I could leave it at that, but in the next case, Oswald v. Landmark Builders, Inc., 97 Cal.App.5th 240 (2023), was too interesting to pass up.
The Oswald Case
On June 28, 2016, homeowners Jack Oswald and Anne Seley sued their general contractor and its subcontractors alleging construction defects at their home. Answers and cross-complaints were filed and on February 2017 the trial court determined the case to be complex and appointed a discovery master. A discovery master, for those who may be unfamiliar, is usually a retired judge or third-party lawyer appointed by a court to oversee discovery in a case such as written discovery, depositions, site inspections, etc.
Mr. Murai may be contacted at gmurai@nomosllp.com