Recovering For Inflation On Federal Contracts: Recent DOD Guidance On Economic Price Adjustment Clauses

Economy text on wood background

In the construction industry, the higher prices of goods and services directly affect how contractors draft their construction contracts.

October 24, 2022
Amanda L. Marutzky - ConsensusDocs

Since October 2020, inflation in the United States has seen its fastest increase in more than 30 years. In the last year alone, inflation has remained as high as 8.6%. This hike has impacted everything from diesel to steel. In the construction industry, the higher prices of goods and services directly affect how contractors draft their construction contracts.

The Department of Defense (DoD) has taken note of this dramatic price increase and recently issued guidance to its commanding officers and the procurement community. On May 5, 2022, DoD issued a memorandum titled “Guidance on Inflation and Economic Price Adjustments.” The stated purpose of the memo is “to assist COs to understand whether it is appropriate to recognize cost increases due to inflation under existing contracts as well as offer considerations for the proper use of EPA when entering into new contracts.” DoD’s memo responds to contractor and contracting officer concerns about the sudden and unexpected cost increases in labor and materials.

Economic Price Adjustments, or EPAs, are adjustments to a stated contract price upon the occurrence of certain contingencies. FAR 16.203-1. They are of three general types – (1) adjustments based on established prices, (2) adjustments based on actual costs of labor or material, or (3) adjustments based on cost indexes of labor or material. Id. Because EPAs allow for adjustments in a contract price, EPA clauses allow a contractor to recover unanticipated increases in its project costs. For example, FAR 52.216-4, Economic Price Adjustment-Labor and Material, authorizes a contractor to recover for increases in the cost of material or labor. Such recovery is available when costs increase more than 3%, with a maximum recovery of 10% of the original contract price. See also FAR 52.216-2 through FAR 52.216-4. These EPA clauses provide contractors with relief and protection from issues such as dramatic inflation. EPA clauses, however, are not included in all contracts.

Ms. Marutzky may be contacted at amarutzky@watttieder.com



714.701.9180

Arrange No Cost Consultation










Subscribe to Construction Defect Journal

Construction Defect Journal Archives - Recent CD News for Construction Claims Professionals

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2024 - Construction Defect Journal – All Rights Reserved